Proposed Funding

It was originally estimated that the refurbishment programme would cost £3.5M but due to increases in the cost of building supplies the project will now cost £4.25M

Funder
Amount
Status
Anglo-Irish
300,000
Awaiting decision
Belfast Regeneration Office
900,000
Awaiting decision new application to be made
National Lottery Heritage Fund
950,000
Stage 1 approved
National Lottery Arts Fund
250,000
Letter of Offer made
National Lottery Charities Board
200,000
Early application made
International Fund for Ireland
600,000
Letter of Offer made
Private Donor
100,000
Secured
Conway Mill Contribution
200,000
100,000 secured to date
European Structural Funds
500,000
Awaiting information
Bank Loan
250,000
Discussions initiated
TOTAL
4,250,000

 

Back to Top

 

 

 

 

 

 

Verticom